UNFCCC
has neither the mechanism to credibly assess the projects, nor the will
to ensure that only eligible projects get credits.
Climate change is the buzz word for everyone these days and one of the
most important efforts of the world in tackling this problem is
supposed to be the projects taken up under the Clean Development
Mechanism (CDM). The controversial 192 MW Allain Duhangan hydropower
project (ADP) (under construction in Himachal Pradesh) is the largest
among all the hydropower projects from all over the world registered to
get credits under CDM.
It is also slated to get the largest number of credits, at around 4.94
million CERs (Certified Emission Reduction credits). At the current
market rate of around $16 per CER, the project is slated to get around
$ 75 M for reducing the impact of climate change. This project does not
deserve to either be called clean or green project, nor does it deserve
to get any of these credits.
The CDM projects are taken up under the United Nations Framework
Convention on Climate Change (UNFCCC), following the Kyoto protocol. To
achieve certain reduction in the emissions of gases the developed
countries could also fund projects in developing countries that help
achieve this. The developed countries would get the credits for the
reduction that would become possible through such funding.
To certify if certain project qualifies for such credits, the UNFCCC
was set up. The process of considering the projects for CDM started in
mid 2004 and the first ever project was registered in November 2004.
UNFCCC has certain criteria that it follows to see if a certain project
is eligible to get the credits. One of the criteria is that the project
must be additional, that is, it would be unviable to take up the
project in the absence of such credits. Other criteria included the
project employing a new technology which rendered costs too high. Also
if the project was making extra efforts to take care of the social and
environmental impacts of the projects, it may require extra funding.
Now let us examine the ADP under construction in Beas River basin near
Manali in this context. Here are some relevant dates in that regard.
The project developer signed the memorandum of understanding with the
Himachal Pradesh government in 1993. In 1996, the environment impact
assessment was conducted. The Central Electricity Authority (CEA) gave
its in principle Techno Economic clearance (TEC) in March 1996, which
certified that the project is economically viable. In August 2002, the
CEA gave its final TEC, following an application by the project
authority in May 2001. The project was supposed to go to the board of
the World Bank for approval for funding in October 2003.
This series of events all before the UNFCCC when they started
considering projects for CDM, shows that the developer was interested
in this project well before the issue of CDM became a reality. Secondly
it also means that the developer considered it a viable project.
The developer also applied for and got the in principle and final TEC,
without any mention of necessity of CDM credits for making the project
viable. The ADP developer himself had taken up the Malana HEP in the
nearby area without the CDM credits, completed it and declared that it
was a very profitable project.
It is also interesting to know that ADP is India’s first merchant
hydropower project. This means that the project developer will not have
any power purchase agreement with any electricity board or distribution
company. It would rather sell the project based on short term contracts
based on spot market prices.
What this implies is that the project developer found the project so
economically viable that he decided to forgo the relative safety of
Power Purchase Agreement (PPA) and was ready to take up the risk of
merchant sale. The project was thus more viable than most other
hydropower projects that require PPA.
Moreover, in the Environment and Social Impact Assessment for the
project done in May 2003, it is stated (page 7), “The project would be
one of the cheapest sources of power generation in the northern region
as compared to alternative of thermal and nuclear generation.”
Why should a project that is supposed to be the cheapest source of
power, be even considered for CDM credits? The ADP is not using any new
technology either. Next, ADP is not taking any extra efforts to ensure
that social and environmental issues are properly taken care of and the
local people are also made beneficiary of the development project.
In response to SANDRP’s (South Asian Network on Dams, Rivers and
People) application under the Right to Information Act, the Union
Ministry of Environment and Forests has agreed that the project
developers have been found to be guilty of scores of violations of the
laws and have been fined for the same. At the local level, a strong
movement has been ongoing against the project since the project
consideration started in 2003.
This project got these fraudulent credits because UNFCCC has neither
the mechanism to credibly assess the projects, nor the will it seems,
to ensure that only eligible projects get credits under CDM.
UNFCCC has basically two ways of ascertaining the eligibility of the
projects for CDM credits. Firstly, there are the designated national
authorities. The environment ministry at the centre certifies if the
project falls under the definition of sustainable development or not.
The govts see CDM credits as free gifts and they are not interested in
bothering too much (or rather at all) if the projects that are
submitted to them are indeed sustainable or not.
Then there are supposed to be independent agencies called
Designated Operational Entities. These are some registered global
consultancy organisations that are supposed to act as validators and
verifiers of the appropriateness of the projects. These are commercial
entities and they can sustain only if they get more work for validation
and verification. If they start becoming particular about
appropriateness of the project, they would rather lose all business.
Moreover, they know that UNFCCC has no way of cross checking whatever
they write in their reports. So this has also proved to be a failed
mechanism. All this has been communicated to the UNFCCC but this global
organisation has yet to respond in a way that will inspire any
confidence.
http://www.deccanherald.com/Content/May152008/editpage2008051467934.asp
Copyright 2007, The Printers
(Mysore) Private Ltd.