Three years after the monster tsunami
hit parts of
coastal India, one would have expected homes for the homeless to have
been constructed by now, especially with funds flowing from all over
the world.
But a UN report on its own efforts says only half the number of homes
that were to be built have been completed so far.
Lack of funds is the least of problems here. The UNDP, in its report,
"Tsunami India: Three years after," says the UN agencies had $44.51
million at the disposal, including contributions from funding agencies
and countries. Of this, $5.30 million was for housing, water and
sanitation.
The largest amount was for health, hygiene and education, though it is
not indicated how many schools or hospitals were destroyed by the
tsunami or how many were re-built.
On the housing programme, the report says out of 53,323 houses planned
to be built as part of the first phase of reconstruction, 29,446 have
been completed to date, while 23,879 are in the process of being built.
Only 20 per cent of the total 214 sites have complete infrastructure,
meaning electricity and water. The report goes on to say that while the
Tamil Nadu public-private partnership model has been innovative in many
ways, it has faced many challenges.
First, although the work of constructing houses was given to a large
number of organisations, the progress has been slow. To date, only 50
per cent houses have been completed. Second, the government faced the
dilemma of ensuring that the people were not displaced to places far
away from their earlier habitat and source of livelihood. There were
difficulties in acquisition of land as the size of the land required
was often large. As a compromise, in several instances, land not
suitable for constructing houses was identified. Third, there have been
delays in provision of basic infrastructure, such as electricity,
water, sanitation and roads. Some delays can be attributed to
limitations in the coordination between various departments responsible
for providing infrastructure.
Fourth, there have been limitations in monitoring construction, leading
to poor-quality housing in some places in terms of materials used,
designs, construction methods and techniques. Fifth, with a few
positive exceptions, the approach has been building houses, rather than
developing habitats. The housing programme would have benefited from a
more holistic approach if various dimensions of housing such as
community infrastructure, water, sanitation, environment, conservation
and livelihood had been addressed in a more integrated and timely
manner. Indeed, in several sites, it has been observed that houses were
handed over to beneficiaries without infrastructure and services
readily available.
This is the UN way of saying that the entire housing programme has been
a fiasco.
The UN report next goes on to identify the main culprits. It says :
"The fact that a major part of housing reconstruction was done by NGOs
who work at the the grassroot level helped improve the beneficiary
participation but not to the level desired.''
"While initial consultations were often made with the beneficiaries,
the participation has been minimal in follow-up planning, design and
quality monitoring. This affected not only the level of satisfaction of
the beneficiaries but also the quality of habitat development as well
as the level of ownership and sustainability of the programme."
Ultimately, the government emerges as the angel here. The report goes
on to say: "The government is taking measures to improve this in the
second phase of reconstruction and the state housing policy, to ensure
that the beneficiaries participate in all stages of housing
reconstruction. To be successful in this, it is essential that the
beneficiary participation takes place within a clearly defined and
standardised institutional framework, which is embedded in local
governance structures and involving strong and representative NGOs to
facilitate the process of community participation. In isolation from
existing legal frameworks, such as panchayats, the beneficiary
participation will lack accountability. This necessitates the
delineation of role and powers of panchayats in the implementation of
rural housing.''
The conclusion is that the entire housing programme was undertaken
without the participation of the affected people and this annuls the
advantage of all the funds at disposal and all the do-gooders available
to use the funds.
The report does not hint at abuse of funds but it does suggest that
they have not served the purpose of bringing relief to the communities
who have been so severely tested by nature.
http://business-standard.com/common/storypage_c.php?leftnm=10&autono=306902
Business Standard Ltd. Copyright &
Disclaimer